The Delft University of Technology’s Faculty of Applied Sciences is currently housed in a number of aged buildings spread over the university’s campus.
It is to house the departments of Biotechnology, Bionanoscience and Chemical Engineering in a single, modern and flexible building that meets the rigid requirements of advanced and leading research.
TNW-buitenkant

Project information

Disciplines

Project Management

Place

Delfr

Client

TU Delft Faculty Management

Architect

Ector Hoogstad Rotterdam

Project size

30.000m2 GFA

Start of project

June 2014

Completion

2016

Consulting services

Complete construction management, (co)creating project brief
chevron-right chevron-left

For the new construction of the Delft University of Technology’s Faculty of Applied Sciences, Aronsohn Management provides integral project management. The objective is to realise housing for the three departments.

Extensive preliminary research has led to the Board of Director’s decision to realise the new building on the campus’ south side, close to the Reactor Institute. Aronsohn has contributed to the creation of the project brief which envelopes offices, education spaces and a great number of high tech laboratories, many of which have to be as good as free of vibrations and pose high requirements to building services. The total surface is approximately 30.000m2 GFA.